Weekly Meetings
Here is a log of activities preformed on a weekly basis with our project sponsor.
Meeting #20 - 07/10/2023
Start - 12:05 PM
End - 12:55 PM
Discussion:
-
July 28 Friday Morning at 9:00am
-
Show organization of presentation - 30 minute presentation
-
Introduce project clearly - first slide
-
Present clear requirements of the project
-
Background information - No need to describe the details of the hardware, just why we chose it
-
Main concentration should be on chapter #3 of the report
-
Original contribution
-
Testing
-
Results
Deliverables
-
Report updates
-
Presentation notes
-
Present TOC.
-
Clearly state project.
-
Only mention why we chose to use certain components
-
Main thing is chapter 3 which is main contribution and testing.
-
Change report title page course number to EET 4950
-
Fix the market comparison missing again on website
-
Double check the budget for some of the items - Updated by Bryan - James GPIO Part
-
Adjust spacing on acknowledgements page.
-
Take the number off the first page
-
Fix align to align left on Second page
-
Add chapter names to each chapter in TOC - James
-
Appendix C to include code. - James
-
Appendix C.1 or C.2
-
List of figures to be normal capitization, not all caps for everything.
-
Update the website with new engineering specifications - Bryan
-
In chapter 1, mention what is going to be presented.
-
One line spacing between sections not double.
-
Section 2.1.6 update display to 7 inch - Bryan
-
Write in the present tense.
-
Add images of the buck regulator and power switch with part numbers - Bryan
-
Chapter 3 to next page. Start all chapters on their own page. - James
-
Chapter 3 should be part of the summary for chapter 3
-
Update figure 3.1
-
Change the hardware designs as a paragraph.
-
Update 3.4 room
-
Add verbiage to hardware design section
-
Hardware section to be updated with the device inside the case
-
Troubleshooting has too much luckliy
-
Move GPIO to medium level
-
Less use of luckily in 3.4
-
3.7.2 formatting and relabel to GPIO interface.
-
How to format the timeline to landscape - James
-
Mention survey questions are from proposal phase - update description in the appendix
-
Add medium or low level requirement for battery timeline
Meeting #19 - 06/27/2023
Began - 12:02 pm
Adjourned - 12:18pm
Discussion:
-
Next Tuesday flying out of town
-
Testing should be done by two weeks and report in final phase
-
July 21st report is due
-
The fan has a decent impact on the temperature inside of the case but not on the heatsink
Deliverables
-
Make a final testing an results tab need to be added to website
-
Each engineering requirement testing is done separately.
-
Need to add testing results of temperature and put them in the log.
-
Testing on vehicles
-
Need to make up a checklist for engineering requirements
-
Testing should be done in two weeks
-
Review the report, most should be written by then
Meeting #18 - 06/20/2023
Began - 12:00 pm
Adjourned - 12:23 pm
Discussion:
-
Majority of GUI done
-
Speak to Dr. Davis about patent idea
-
Work on specific test documents for each test
Deliverables
-
Testing the Device next week on the vehicle
-
Should have final print done this week
-
Need to do more testing on the temperature of the device without the fan running
-
Temperature sensor cleanup
-
Testing on an actual vehicle and start to fill out test requirements
-
Start working on report
Meeting #17 - 06/13/2023
Began - 12:03 pm
Adjourned - 12:23 pm
Discussion:
-
Results at 10,000 mA battery ran for hours
-
Changed to 200mA battery that is also rechargeable
-
Bryan did testing that was informal - need to setup a timer and get numbers.
-
New file
-
July 28th will be the presentation at 9:00am
-
40 bucks for the case
Deliverables
-
Continuity testing for data lengths that are not the correct lengths.
-
Work on local filtering
-
One Wire GPIO
-
GPIO input into programming
-
Log the data from temperature readings on the PI
-
Work on the wireless settings to configure
-
3d Printed case construction this week
-
Update what needs to be changed in the case.
-
Meeting #16 - 06/06/2023
Began - 12:03 pm
Adjourned - 12:23 pm
Discussion:
-
Discussion on future testing running off 12volt
Deliverables
-
Plan to have the box ready by next Tuesday
-
Have the work done on the GUI
-
Incorporate the GPIO and the database functioning
-
Change over the video to use Youtube and not a video file.
-
Meeting #15 - 05/30/2023
Began - 12:01 pm
Adjourned - 12:17 pm
Discussion:
-
Update the time and effort log for google.
-
Matplotlib will update as often as the CAN message comes in
-
Discussed how the multithreading will have to work to overcome current GUI issues with waiting for CAN messages.
-
We can use the openlab for 3d printing if in PLA, or use the 3d printing lab with ABS, we just need to reach out to Will.
Deliverables
-
Deliverables:
-
Make a separate page for the Gantt timeline
-
Get multi-threading working for the CAN Bus and incorporate into the HMI display
-
Bryan to work on the three bottom buttons, wireless, setting, and vehicle.
-
Bryan to update the time and effort log
Meeting #14 - 05/23/2023
Began - 12:00 pm
Adjourned - 12:23 pm
Discussion:
-
Better format the buttons on the GUI.
-
Option for a manual switch should be utilized first.
-
Need to do heat testing with the heat sink and see if a fan is necessary
-
How is automatic switching done
-
3d Printer at Valencia at the Open Lab - Neil or Daniel.
Deliverables
-
Actual project timeline.
-
Work on bottom option on GUI.
-
Work on Top of GUI and incorporating the database for the hardware.
-
Put some more distance between.
-
Start working on CAD rendering.
-
Update the budget with new components if not there.
-
Shift more focus to the GUI stuff.
-
Add sim card into the budget.
-
Add fan to budget.
-
CAD drawing for casing
-
Testing SIM card dongle with power
-
Get system powered and a 12 V battery.
-
Meeting #13 - 05/16/2023
Began - 12:00 pm
Adjourned - 12:20 pm
Discussion:
-
Think about having the RPi autoselect between wireless modes.
Deliverables
-
Battery purchase
-
Voltage selector
-
Monitor
-
GUI in Tkinter
-
Dongle for the SIM Card
-
Add an actual timeline as we are moving along.
Meeting #12 - 05/09/2023
Began - 12:00 pm
Adjourned - 12:26 pm
Discussion:
-
Figure out a meeting time.
-
Feedback from proposal presentation in an email from Dr. Ejaz
-
Chapter 2 in the proposal will be moved to Chapter 1 in the design report.
-
Chapter 3 will be the majority of the report and show progress, data analysis, etc...
Deliverables
-
New meeting times are 12pm to 1pm on Tuesdays.
-
Review feedback from industry professionals
-
Review the rubric in Canvas for the design of the project
-
Add the usb dongle to the new budget
-
Change dates around and keep up to date on progress log.